Enhancing and Protecting Interventions along Rajpur- Tikkhatar District Road
Program Period : 6th May, 2004 to 6th June, 2005
Funding Agency(s) : Office of the District Development Committee/RAP/RCIW,
Program Area : 4 VDCs (Ranagaon, Durgamandu, Basudeviand Tikhatar) along the alignment of Dipayal- ChawaraChautara (Rajpur- Tikhatar Section) District Road of Doti
Objective of Program
• To provide sustainable social and economic benefits from the construction of roads and provide access to services, markets.
• To create awareness.
• Involve the beneficiaries in the road construction process.
• To increase the income of the road construction committee members.
• To increase the capacity of marginalized communities and involve them in the decision-making process.
• To capacitate the road construction group beneficiaries in keeping general accounting.
Program Output
• A total of 81 road construction groups were formed and mobilized.
• A total of 1602 members (881 females and 721 male) supported road construction.
• First aid medicine was distributed to 81 groups.
• Various types of training were conducted for the members of the group
– Training was conducted on Compost making-97
– Gabion Wire weaving-15
– Group Management and Leadership-162
– Conflict Management-162
– Health and Sanitation-162
– Saving and Credit- 162
– Literacy facilitation- 81
– Improvised cooking- 20
• The beneficiaries were supported with 24,633 kg of rice and NRs. 786,715 for their work.
• Among them 25 groups have created a saving amount of NRs. 78,670 as 10% of the money provided to them.
• 36.590 km of road was constructed.
• Skill development and enterprise development and market coordination were conducted during and after the completion of road construction.
• Social mobilization, saving and credit mobilization, literacy, and non-formal education were conducted for the members of the group formed.